PROJECT

Schedule

Spring 2018: Land secured with original developer

Summer 2018: Land purchased by ABO Wind

September 2018: Stakeholder consultation begins

December 2018: Additional land secured (land base extended)

December 2018: First meteorological mast erected

Spring 2018: Environmental studies begin

March 27, 2019: First open house

June 2019: Entered AESO Queue

November 28, 2019: Second open house

December 2019: Second meteorological mast erection

Fall 2020: AUC Application

Winter 2022: AUC Approval

Spring 2023: Anticipated date of construction

Fall 2024: Target Commercial Operations Date (COD)

2048: Anticipated decommissioning and reclamation

Schedule is preliminary and subject to change.